SLIPFORM : Summary Of Labour Productivity Norms


SL NO.
TYPES OF WORK
UNIT
NORMS IN M/Hours
1
Erection of Access Tower (2.5 X 2.5 M)
RM
32
2
Dismantling of Access Tower (2.5 X 2.5 M)
RM
15
3
Erection of Stair Tower (2.5 X 2.5 M)
RM
16
4
Dismantling of Stair Tower (2.5 X 2.5 M)
RM
8
5
Straight Slipform Assembly
YOKE SET
75
6
Straight Slipform Dismantling
YOKE SET
55
7
Slipform Operation - Straight Slipform
M2
1.22
8
Assembly of Pre-Stressed Silo
YOKE SET
92
9
Slipform Concrete - Manual
M3
22
10
Slipform Concrete - Rmc With Pump
M3
15
11
Slipform Concrete - Rmc With Hoist
M3
25
12
Slipform Reinforcement - Straight Slipform
MT
65
13
Extraction of Climbing Rod
RM
0.34
14
Taper Slipform Assembly - Upto 24 Yoke Set
MT
56
15
Taper Slipform Assembly - 16 To 48 Yoke Set
MT
49
16
Taper Slipform Dismantling - Upto 24 Yoke Set
MT
49
17
Taper Slipform Dismantling - 16 to 48 Yoke Set
MT
46
18
Re-Assembly of Slipform - Taper Slipform
MT
78
19
Re-Assembly of Slipform - Straight Slipform
YOKE SET
90
20
Slipform Operation - Taper Slipform
M2
2.45
21
Slipform Reinforcement - Taper Slipform
MT
90
22
Erection of R.G.Hoist
NOS
827
23
Re-Location of R.G.Hoist
NOS
1365
24
Dismantling of R.G.Hoist
NOS
675
25
Pre-Stressing Works in Silos
MT
170

Note : The productivity norms will vary based on volume of work involved and number of structures to be constructed in the project.
_________________________________________________________________________________

Official Website  

Official Website

Download OfficialApp

Download App For Interview

YouTube Channel

Facebook Page

Twitter

Pinterest

Instagram

Google plus

Email Id
civilengineeringofficial@gmail.com